Site Control and Traversing: Check the Control Before Setting Out

Before setting out a drain, a foundation or a line of kerbs, I want to know the control is right. A coordinate file and a few nails in the ground are a starting point. They still need checking.

Site control is the network of reference points used to keep survey and setting-out work on the same coordinate system and level datum. A traverse links control points through measured angles and distances. Done properly, it gives the site team a checked basis for setting out, as-built surveys and dimensional checks.

Start with the grid, datum and existing control

First, establish what the project is actually using. Is it an OS grid or a local site grid? What is the height datum? Which control schedule is current, and what checks support it? The drawing coordinates, survey data and instrument job must agree.

Grid-to-ground scale also matters. A distance on a projected grid is not automatically the same as a distance measured on the ground. If a scale factor or site transformation is needed, it should be understood, agreed and recorded. Changing a scale simply to make a check fit can hide the real problem.

What a traverse checks

A total station traverse carries position and orientation between stations. Closing back onto the starting control, or connecting to suitable known control at the other end, provides checks on the observations. The network geometry and the quality of the starting control still matter.

A small misclosure is useful evidence. It does not, by itself, prove that the whole network is on the correct grid or datum. A network can agree well internally and still be in the wrong place. Where suitable independent control is available, checking against points that were not used to force the adjustment gives another useful test.

The fieldwork matters as much as the adjustment

I would rather investigate a doubtful observation while the instrument is still set up than find it later in the office. Stable stations, careful centring, the correct prism constant, recorded instrument and target heights, and suitable atmospheric settings all matter.

Observations on both faces and repeated sets, where required by the survey method, help assess consistency. They do not cure every error. Repeating the same wrong target height or working from a disturbed control point can produce repeatable results that are still wrong.

Control also needs to survive the job. Put points where they can be used safely and where excavation, plant or stored materials are less likely to disturb them. Record the point IDs and locations so the next engineer can identify them.

Adjustment is a check, not a way to hide bad observations

A least-squares adjustment can use the available observations and their estimated precision to calculate coordinates and assess the network. The residuals, statistical checks and estimated coordinate uncertainty need reviewing against the survey requirements.

If something fails, look for the reason: point identification, centring, heights, instrument settings, poor geometry or inconsistent existing control. Removing an observation or changing its weight needs a defensible reason. Getting a report to pass is not the same as establishing reliable control.

Where does GNSS fit?

GNSS can help establish or check a site’s relationship to the wider coordinate system. A total station can then provide the local observations needed around the works. They are useful together, but they do not have identical uncertainties or suit every location.

If GNSS and total station results disagree, compare the coordinate system, transformation, height reference, observation conditions and expected uncertainty before deciding which result to use. Avoid treating a single GNSS fix as proof of a tight construction tolerance.

What should the site team receive?

Agree the deliverables before the survey. A useful control handover can include:

  • A dated coordinate schedule with point IDs, eastings, northings and levels.
  • The coordinate system, level datum and any agreed transformation or scale factor.
  • A location plan, descriptions or photographs of the control points.
  • The relevant traverse, adjustment and check records, with limitations clearly stated.
  • A clear record of revised or withdrawn points so old coordinates are not reused.

Control needs checking again when points may have moved and as the site develops. It supports the whole job, from the first setting out to the final as-built records.

Site control and setting out in Cornwall and Devon

DLPCivils Ltd provides setting out, site control, as-built surveys and QA support across Cornwall, Devon and the South West. You can see how control supported survey work in our drone survey, site control and setting-out project.

Need existing control checked or control established for upcoming work? Send Darren the site location, current control schedule, drawings and required scope. Call 07482413138 or get in touch. Our site-visit checklist covers the information to send beforehand.

Related posts

Leave the first comment